ESCO Highlights

For....      

Black_Bar_Stahl.jpg

 

Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Substantially Complete August 3, 2009
FIO #2 Upgrade Fire Alarm System Substantially Complete February 12, 2010
FIO #3 Lighting Retrofit Substantially Complete June 18, 2009
FIO #4 Water Retrofit Substantially Complete July 30, 2009

 

 Projected dates subject to change.  Please check back regularly for updates.

Last updated:  June 16, 2010