ESCO Highlights
For....
| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
Substantially Complete |
July 10, 2009 |
| FIO #2 Lighting Retrofit |
Substantially Complete |
June 3, 2009 |
| FIO #3 Water Retrofit |
Substantially Complete |
September 14, 2009 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|
|