Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Projected July 12 - 30, 2010
FIO #2 Upgrade Fire Alarm System Projected July 12 - 23, 2010
FIO #3 Lighting Retrofit Substantially Complete June 23, 2009
FIO #4 Water Retrofit Substantially Complete July 27, 2009
FIO #5 Upgrade Zoning System Projected July 12 - 30, 2010
FIO #6 Supplemental Cooling for Dispatch Safe Room Substantially Complete August 12, 2009

 

Projected dates subject to change.  Please check back regularly for updates.

Last updated:  June 16, 2010