ESCO Highlights
For....
| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
Substantially Complete |
August 17, 2009 |
| FIO #2 Upgrade Fire Alarm System |
Substantially Complete |
February 3, 2010 |
| FIO #3 Lighting Retrofit |
Substantially Complete |
August 26, 2009 |
| FIO #4 Water Retrofit |
Substantially Complete |
July 27, 2009 |
| FIO #5 RTU Replacement |
Substantially Complete |
August 13, 2009 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|