ESCO Highlights

For....      

Black_Bar_Multipurpose.jpg

 

Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System In Progress April 5 - July 6, 2010
FIO #2 Upgrade Fire Alarm System Projected July 19 - Sep 10, 2010
FIO #3 Lighting Retrofit (except Gym) Substantially Complete September 11, 2009
FIO #4 Water Retrofit Substantially Complete August 18, 2009
FIO #5 Thermal Equalizers in Arena Substantially Complete May 4, 2010
FIO #6 Chiller Replacement Substantially Complete Jan 11 - March 12, 2010
FIO #7 Boiler Replacement Confirmed June 21 - July 30, 2010
FIO #8 Rebalance 2nd Floor Ductwork Substantially Complete September 4, 2009
FIO #9 Upgrade Pool Enclosure Substantially Complete July 17, 2009
FIO #10 Add Water to Water Heat Pump for Domestic Hot Water Confirmed June 21 - July 23, 2010

 

Projected dates subject to change.  Please check back regularly for updates.

Last updated:  June 16, 2010