ESCO Highlights
For....
| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
In Progress |
April 5 - July 6, 2010 |
| FIO #2 Upgrade Fire Alarm System |
Projected |
July 19 - Sep 10, 2010 |
| FIO #3 Lighting Retrofit (except Gym) |
Substantially Complete |
September 11, 2009 |
| FIO #4 Water Retrofit |
Substantially Complete |
August 18, 2009 |
| FIO #5 Thermal Equalizers in Arena |
Substantially Complete |
May 4, 2010 |
| FIO #6 Chiller Replacement |
Substantially Complete |
Jan 11 - March 12, 2010 |
| FIO #7 Boiler Replacement |
Confirmed |
June 21 - July 30, 2010 |
| FIO #8 Rebalance 2nd Floor Ductwork |
Substantially Complete |
September 4, 2009 |
| FIO #9 Upgrade Pool Enclosure |
Substantially Complete |
July 17, 2009 |
| FIO #10 Add Water to Water Heat Pump for Domestic Hot Water |
Confirmed |
June 21 - July 23, 2010 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|