Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Substantially Complete December 1, 2009
FIO #2 Upgrade Fire Alarm System Substantially Complete

April 22, 2010

FIO #3 Lighting Retrofit Substantially Complete October 30, 2009
FIO #4 Water Retrofit Substantially Complete August 3, 2009
FIO #5 Constant Volume Dual Duct to VAV Dual Duct Conversion Substantially Complete September 4, 2009
FIO #6 Upgrade AHUs Substantially Complete April 8, 2010
FIO #7 Boiler Replacement In Progress Nov 9 - June 25, 2010
FIO #8 Chiller Replacement Substantially Complete April 14, 2010
FIO #9 Fume Hood Replacement Confirmed June 21 - Aug 13, 2010
FIO #10 Install New Emergency Generator In Progress April 1 - July 14, 2010
FIO #11 Roof Section Repair Substantially Complete August 26, 2009
FIO #12 Ceiling Removal Substantially Complete July 20, 2009
 FIO #12 Ceiling Replacement Substantially Complete October 16, 2009
FIO #13 Pump Replacement Substantially Complete December 28, 2009
FIO #14 IAQ DDC Controls Sequence of Operations Deleted March 15 - April 16, 2010
FIO #15 Fire Sprinklers Substantially Complete October 16, 2009

Projected dates subject to change.  Please check back regularly for updates.

Last updated:  June 16, 2010