ESCO Highlights
For....
| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
Substantially Complete |
December 1, 2009 |
| FIO #2 Upgrade Fire Alarm System |
Substantially Complete |
April 22, 2010 |
| FIO #3 Lighting Retrofit |
Substantially Complete |
October 30, 2009 |
| FIO #4 Water Retrofit |
Substantially Complete |
August 3, 2009 |
| FIO #5 Constant Volume Dual Duct to VAV Dual Duct Conversion |
Substantially Complete |
September 4, 2009 |
| FIO #6 Upgrade AHUs |
Substantially Complete |
April 8, 2010 |
| FIO #7 Boiler Replacement |
In Progress |
Nov 9 - June 25, 2010 |
| FIO #8 Chiller Replacement |
Substantially Complete |
April 14, 2010 |
| FIO #9 Fume Hood Replacement |
Confirmed |
June 21 - Aug 13, 2010 |
| FIO #10 Install New Emergency Generator |
In Progress |
April 1 - July 14, 2010 |
| FIO #11 Roof Section Repair |
Substantially Complete |
August 26, 2009 |
| FIO #12 Ceiling Removal |
Substantially Complete |
July 20, 2009 |
| FIO #12 Ceiling Replacement |
Substantially Complete |
October 16, 2009 |
| FIO #13 Pump Replacement |
Substantially Complete |
December 28, 2009 |
| FIO #14 IAQ DDC Controls Sequence of Operations |
Deleted |
March 15 - April 16, 2010 |
| FIO #15 Fire Sprinklers |
Substantially Complete |
October 16, 2009 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|
|