ESCO Highlights
For....
| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
Substantially Complete |
March 5, 2010 |
| FIO #2 Upgrade Fire Alarm System |
Substantially Complete |
January 15, 2010 |
| FIO #3 Lighting Retrofit |
Substantially Complete |
June 24, 2009 |
| FIO #4 Water Retrofit |
Substantially Complete |
August 6, 2009 |
| FIO #5 Constant Volume Dual Duct to VAV Dual Duct Conversion |
Substantially Complete |
March 5, 2010 |
| FIO #6 Make-Up Air Installation for Firing Range |
Substantially Complete |
August 28, 2009 |
| FIO #7 Front Balcony Roof Repair |
Substantially Complete |
July 28, 2009 |
| FIO #8 Upgrade AHUs |
Substantially Complete |
March 5, 2010 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|