ESCO Highlights
For....
| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
Substantially Complete |
October 1, 2009 |
| FIO #2 Upgrade Fire Alarm System |
Substantially Complete |
January 29, 2010 |
| FIO #3 Lighting Retrofit |
Substantially Complete |
June 23, 2009 |
| FIO #4 Water Retrofit |
Substantially Complete |
July 28, 2009 |
| FIO #5 RTU & UH Replacement |
Substantially Complete |
September 23, 2009 |
| FIO #6 Rebalance Airflow |
Substantially Complete |
September 29, 2009 |
| FIO #7 Single Pane Window Replacement |
Substantially Complete |
July 17, 2009 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|
|