ESCO Highlights

For....    

Black_Bar_Grinstead.jpg

 

Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System In Progress Dec. 21 - Aug 27, 2010
FIO #2 Lighting Retrofit Substantially Complete July 24, 2009
FIO #3 Water Retrofit Substantially Complete September 3, 2009
FIO #4 Boiler Installation Substantially Complete December 2, 2009
FIO #5 Window Replacement In Progress May 17 - July 29, 2010
FIO #6 Upgrade Make-Up Air & Exhaust in Welding/Carpentry Shops Substantially Complete February 22, 2010
FIO #7 Roof Section Repair Substantially Complete July 31, 2009
FIO #8 Seal Exterior Walls Projected  July 12 - 23, 2010

 Projected dates subject to change.  Please check back regularly for updates.

Last updated: June 16, 2010