ESCO Highlights
For....
| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
In Progress |
Dec. 21 - Aug 27, 2010 |
| FIO #2 Lighting Retrofit |
Substantially Complete |
July 24, 2009 |
| FIO #3 Water Retrofit |
Substantially Complete |
September 3, 2009 |
| FIO #4 Boiler Installation |
Substantially Complete |
December 2, 2009 |
| FIO #5 Window Replacement |
In Progress |
May 17 - July 29, 2010 |
| FIO #6 Upgrade Make-Up Air & Exhaust in Welding/Carpentry Shops |
Substantially Complete |
February 22, 2010 |
| FIO #7 Roof Section Repair |
Substantially Complete |
July 31, 2009 |
| FIO #8 Seal Exterior Walls |
Projected |
July 12 - 23, 2010 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|
|