Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Projected July 19 - Oct 8, 2010
FIO #2 Upgrade Fire Alarm System Projected July 19 - Aug 12, 2010
FIO #3 Lighting Retrofit Substantially Complete August 28, 2009
FIO #4 Water Retrofit Substantially Complete August 26, 2009
FIO #5 Convert Steam Unit Heaters to Infrared at Overhead Doors Deleted July 6 - 19, 2010
FIO #6 Interlock Overhead Doors with New Infrared Heaters Deleted July 6 - 12, 2010
FIO #7 Install Make-Up Air and Exhaust in Print Shop Projected July 12 - 16, 2010
FIO #8 Upgrade Air Compressor in Paint Shop Projected Aug 30 - Sept 3, 2010
FIO #9 RTU Replacement Projected

July 12 - 30, 2010

FIO #10 Boiler Replacement Projected Aug 30 - Sep 24, 2010

Projected dates subject to change.  Please check back regularly for updates.

Last updated:  June 16, 2010