ESCO Highlights
For....
| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
Projected |
July 19 - Oct 8, 2010 |
| FIO #2 Upgrade Fire Alarm System |
Projected |
July 19 - Aug 12, 2010 |
| FIO #3 Lighting Retrofit |
Substantially Complete |
August 28, 2009 |
| FIO #4 Water Retrofit |
Substantially Complete |
August 26, 2009 |
| FIO #5 Convert Steam Unit Heaters to Infrared at Overhead Doors |
Deleted |
July 6 - 19, 2010 |
| FIO #6 Interlock Overhead Doors with New Infrared Heaters |
Deleted |
July 6 - 12, 2010 |
| FIO #7 Install Make-Up Air and Exhaust in Print Shop |
Projected |
July 12 - 16, 2010 |
| FIO #8 Upgrade Air Compressor in Paint Shop |
Projected |
Aug 30 - Sept 3, 2010 |
| FIO #9 RTU Replacement |
Projected |
July 12 - 30, 2010 |
| FIO #10 Boiler Replacement |
Projected |
Aug 30 - Sep 24, 2010 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|
|