ESCO Highlights
For....
| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
In Progress |
May 17 - July 23, 2010 |
| FIO #2 Upgrade Fire Alarm System |
Substantially Complete |
December 30, 2009 |
| FIO #3 Lighting Retrofit |
Substantially Complete |
September 11, 2009 |
| FIO #4 Water Retrofit |
Substantially Complete |
September 15, 2009 |
| FIO #5 Boiler Replacement |
In Progress |
March 24 - July 9, 2010 |
| FIO #6 Window Replacement |
Substantially Complete |
August 14, 2009 |
| FIO #7 Fire Sprinklers |
Substantially Complete |
January 15, 2010 |
| FIO #8 Gallery RTU Replacement |
Substantially Complete |
June 7, 2010 |
|
FIO #9 FCU Modification (Mechanical) |
Substantially Complete |
August 14, 2009 |
| FIO #9 FCU Modification (Controls) |
In Progress |
May 17 - July 9, 2010 |
| PR 004 Accreditation |
Delayed |
Aug 2 - Sept 24, 2010 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|
|