ESCO Highlights

For....   

Black_Bar_Art_Annex.jpg

 

Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Substantially Complete August 5, 2009
FIO #2 Upgrade Fire Alarm System Substantially Complete February 19, 2010
FIO #3 Lighting Retrofit Substantially Complete June 17, 2009
FIO #4 Water Retrofit Substantially Complete July 30, 2009
FIO #5 Insulate Attic Substantially Complete June 10, 2010

 

 

Projected dates subject to change.  Please check back regularly for updates.

Last updated:  June 16, 2010