ESCO Highlights

For.... 

 Black_Bar_-_admin_hendricks.jpg 

 

Work Item Schedule Status Dates
FIO #1 Upgrade Building Automation System Substantially Complete February 22, 2010
FIO #2 Lighting Retrofit Substantially Complete October 23, 2009
FIO #3 Water Retrofit Substantially Complete August 20, 2009
FIO #4 Convert to Hybrid Geothermal Heat Pump System  Substantially Complete

January 21, 2010                    

FIO #5 Boiler Installation Substantially Complete January 6, 2010
FIO #6 Electrical Upgrades Substantially Complete January 28, 2010
FIO #7 Ventilation Air for Geothermal Heat Pump System Substantially Complete March 2, 2010
FIO #8 Window Replacement Projected July 1 - 21, 2010
Fire Alarm Substantially Complete April 2, 2010 

 

Projected dates subject to change.  Please check back regularly for updates.

Last updated:  June 16, 2010