| Work Item |
Schedule Status |
Dates |
| FIO #1 Upgrade Building Automation System |
Substantially Complete |
February 22, 2010 |
| FIO #2 Lighting Retrofit |
Substantially Complete |
October 23, 2009 |
| FIO #3 Water Retrofit |
Substantially Complete |
August 20, 2009 |
| FIO #4 Convert to Hybrid Geothermal Heat Pump System |
Substantially Complete |
January 21, 2010 |
| FIO #5 Boiler Installation |
Substantially Complete |
January 6, 2010 |
| FIO #6 Electrical Upgrades |
Substantially Complete |
January 28, 2010 |
| FIO #7 Ventilation Air for Geothermal Heat Pump System |
Substantially Complete |
March 2, 2010 |
| FIO #8 Window Replacement |
Projected |
July 1 - 21, 2010 |
| Fire Alarm |
Substantially Complete |
April 2, 2010 |
Projected dates subject to change. Please check back regularly for updates.
Last updated: June 16, 2010
|